Midden Nederland Hallen Barneveld
For the Midden Nederland Hallen in Barneveld, Brink Steel Group delivered the steel structure for a new theater built for the production 40-45 The Musical by Studio 100. The massive building features a column-free span of 75 by 85 meters and reaches a height of 20 meters.
The steel structure, weighing more than 700 tons, was erected in just three weeks — an achievement we are particularly proud of. On November 14, 2023, the topping-out milestone was celebrated together with the client, construction partners, and everyone involved in the project. Brink Staalbouw delivered true craftsmanship with a steel structure that is not only impressive in scale, but also meets the highest standards for quality and safety.